2008 Borough of Chatham Annual Reports
ADMINISTRATOR’S REPORT FOR THE YEAR 2008
Board of Health 2008 Annual Report
Clerks Office 2008 Annual Report
Emergency Management 2008 Annual Report
Emergency Squad 2008 Annual Report
Finance 2008 Annual Report
Fire Department 2008 Annual Report
Fleet Maintenance 2008 Annual Report
Historic Preservation 2008 Annual Report
LIBRARY OF THE CHATHAMS Annual Report 2008
Madison-Chatham Joint Meeting Water Treatment Annual Report for 2008
Mayor State of the Borough Message 2008
Municipal Court 2008 Annual Report
Planning Board 2008 Annual Report
Police Department 2008 Annual Report
Recreation 2008 Annual Report
Registrar 2008 Annual Report
Sign Committee Annual Report 2008
Shade Tree 2008 Annual Report
Tax Assessor 2008 Annual Report
Tax Collector 2008 Annual Report
Welfare Department Annual Report 2008
Zoning Board of Adjustment 2008 Annual Report
 
 

2007 Borough of Chatham Annual Reports
ADMINISTRATOR’S REPORT FOR THE YEAR 2007 (or READ HERE)
Board of Health 2007 Annual Report
Clerks Office 2007 Annual Report
Construction Department 2007 Annual Report
Emergency Management 2007 Annual Report
Emergency Squad 2007 Annual Report
Environmental 2007 Annual Report
Finance 2007 Annual Report
Fire Department 2007 Annual Report
Fire Safety 2007 Annual Report
Fleet Maintenance 2007 Annual Report
Historic Preservation 2007 Annual Report
LIBRARY OF THE CHATHAMS Annual Report 2007
Madison-Chatham Joint Meeting Water Treatment Annual Report for 2007
Mayor State of the Borough Message 2007
Municipal Court 2007 Annual Report
Planning Board 2007 Annual Report
Police Department 2007 Annual Report
Public Works 2007 Annual Report
Recreation 2007 Annual Report
Registrar 2007 Annual Report
Sign Committee Annual Report 2007
Shade Tree 2007 Annual Report
Tax Assessor 2007 Annual Report
Tax Collector 2007 Annual Report
Welfare Department Annual Report 2007
Zoning Board of Adjustment 2007 Annual Report

 
 

2007 GOALS AND OBJECTIVES

1. Prepare and submit the 2007 budget for approval.

Objectives:

  • Compile the budget that was submitted by each department head.
  • Schedule at least one finance committee meeting.
  • Revise the budget.
  • Discuss the budget with the Auditor.
  • Submit the budget for first reading before March 1, 2007
  • Adopt the budget during the month of March 2007.
  • Receive state approval before June 1, 2007.
  • Issue department budgets to each department head, board and commission chair.

2. Goal: Initiate preparation of the 2008 budget by August 1, 2007.

Objectives:

  • Send requests to the department heads, board and commission chairs to prepare and submit their 2008 budgets before September 1, 2007.
  • Initiate budget hearings at the first September Council meeting.
  • Complete budget hearings before December 1, 2007.
  • During the month of January 2008, discuss the 2008 budget with the Finance Committee.
  • During the month of January 2008, meet with the Auditor.
  • Provide written summary of the budget to the Mayor and Council.
  • If necessary, meet with the Finance Committee to finalize the budget.
  • Introduce the budget before March 1, 2008.
  • Adopt the budget during the month of March 2008.

3. Goal Resurface Van Doren Avenue. Objectives:

  • Prepare bid specifications before April 1, 2007.
  • Advertise for bids, May 1, 2007.
  • Award contract for work, June 1, 2007.
  • Initiate work, July 1, 2007.
  • Complete project, September 1, 2007.

4. Goal: Complete the sidewalk maintenance program before September 1, 2007.

Objectives:

  • Request the engineer to complete the sidewalk improvement list before May 1, 2007 and prepare bid specifications.
  • Advertise for bids during the month of May 2007.
  • Award contract before June 1, 2007.
  • Complete the project before August 15, 2007.

5. Goal: Schedule ten monthly department head meetings.

Objectives:

  • Prepare written agendas for each meeting.
  • Invite the Mayor and one or two Borough Council members to attend each meeting.
  • Develop professional development lectures. Guest speakers will be scheduled.

6. Goal: Complete the Jackson Avenue Lift Station project.

Objectives:

  • Receive permit from DEP before March 1, 2007.
  • Complete plan and review with DPW, March 1, 2007.
  • Schedule public information meeting before April 1, 2007.
  • Advertise for bids before May 1, 2007. Award contract before June 1, 2007.
  • Start work before July 1, 2007.

7. Goal: Plan and complete work on the final phases of lighting and sidewalks of the Streetscape Project.

Objectives:

  • Initiate the lighting installation before April 2007.
  • Complete the lighting installation before June 2007.
  • Advertise for the sidewalk installation before March 1, 2007.
  • Advertise for sidewalk bids before April 1, 2007.
  • Award sidewalk installation contract before May 1, 2007.
  • Initiate work before June 1, 2007.
  • Complete the project by December 1, 2007.

8. Goal: Develop backup water well plan and possible new observation well to monitor water quality.

Objectives:

  • Prepare project plan and schedule and present to the Mayor and Borough Council by March 15, 2007.
  • Hold preliminary discussions with New Jersey Department of Environmental Protection by April 1, 2007 and modify plan accordingly.
  • Identify the best sites and backup sites for wells by April 15, 2007.
  • Hold public information meetings with well site neighborhoods by May 1, 2007.
  • Develop preliminary design plans by June 1, 2007.
  • Submit application to New Jersey Department of Environmental Protection by July 1, 2007.
  • Receive New Jersey Department of Environmental Protection approval by September 1, 2007.
  • Develop final plans, specifications and contract documents by October 1, 2007.
  • Review final plans, budget and schedule with the Mayor and Borough Council by October 15, 2007.
  • Advertise for bids for work by November 1, 2007.
  • Award contract by December 15, 2007.

9. Goal: Add 20 new parking spaces at the library.

Objectives:

  • Negotiate revised agreement with St. Paul’s Church, including permanent access easement by March 1, 2007.
  • Develop design plans and specifications by March 1, 2007. Review plans with Mayor and Borough Council by March 1, 2007.
  • Advertise for bids by April 15, 2007.
  • Award contract by May 15, 2007.

10. Goal: Develop and implement a televised community bulletin board and schedule for the rebroadcast of public meetings.

Objectives:

  • Before January 15, 2007, meet with Cablevision to discuss the TelVue system.
  • Develop the public meeting rebroadcast schedule.
  • Post the public meeting rebroadcast schedule on the web page.
  • Before February 15, 2007, decide which bulletin board system will be implemented; TelVue or the Borough’s design.
  • Implement the community bulletin board before March 1, 2007.

11. Goal: Review options for the Woodland Park Project and implement a plan.

Objectives:

  • Schedule the Woodland Park Planning Committee to discuss the options.
  • Present Woodland Park Committee recommendations to the Mayor and Borough Council.
  • If the plan is to continue the development of an athletic field, discuss the development of an Interlocal Agreement; Chatham Township, Chatham Borough and Board of Education.

12. Goal: Develop and implement a plan to improve Memorial Park

. Objectives:

  • The Memorial Park Planning Committee should establish recommendations and prepare a written report for the Mayor and Borough Council by June 2007.
  • Hold public information meeting when the plan is presented to the Mayor and Borough Council.
  • When the concept is approved, complete preliminary design work and discuss with Planning Committee, August 2007.
  • Present final plan to Mayor, Borough Council and the public, September 2007.
  • If approved, advertise for bids, November 2007 • Award Contract, December 2007.
  • Initiate work, March 2008.

13. Goal: Develop and implement a plan to address traffic issues on Elmwood Avenue and Coleman Avenue

Objectives:

  • During the month of January 2007, schedule meetings with representatives from Ogden Church to discuss options.
  • Before February 1, 2007, the engineer will review the issues and provide guidance and alternatives for resolution of the issues.
  • Before March 1, 2007, schedule the matter for discussion with the public and Borough Council.
  • Revise the plan as necessary. If there is consensus, implement plan.

14. Goal: Complete the Borough Hall office relocation plan.

Objectives:

  • Before January 15, 2007, schedule meeting with planning committee to finalize the relocation plan.
  • Implement construction work before February 1, 2007.
  • Complete construction and move offices before April 1, 2007.

15. Goal: Implement new parking meter system.

Objectives:

  • Prepare bid package and advertise for bids before February 1, 2007.
  • Award contract before March 1, 2007.
  • Provide notification to the commuters during the month of March.
  • Install new machines during the month of April.

16. Goal: Pave the Center Street east parking lot.

Objectives:

  • Prepare bid specifications before June 1, 2007.
  • Advertise for bids during the month of June.
  • Award contract before July 15, 2007. • Initiate work before August 15, 2007.
  • Complete the project before September 1, 2007.

17. Goal: Initiate the design for the Parrot Mill and Riverview pumping stations.

Objectives:

  • Before May 1, 2007, the engineer will prepare and submit plans to the Borough Council for review.
  • The plans will be presented to the Mayor and Borough Council at the June Borough Council meeting.
  • When the plans are approved, the project will be advertised for bids. Tentative timeline for advertisement is July, 2007.
  • Award the contract within 45 days of the bid advertisement.
  • Initiate projects before December 31, 2007.

18. Goal: Review Open Space tax and decide whether to continue the tax and whether to expand the uses of its revenues.

Objectives:

  • Prepare timeline and submit to the Mayor and Borough Council, January 10, 2007.
  • Send timeline to the Open Space Committee, February 1, 2007.
  • Schedule Open Space Committee recommendations for the April 23, 2007 Borough Council meeting.
  • Discuss and decide the public information schedule.
  • The decision to place the referendum on the 2007 November ballot will be announced before August 1, 2007.

19. Goal: Complete the Burgess, Chandler and South Passaic road projects.

Objectives:

  • Complete design before April 15, 2007.
  • Advertise for bids before April 20, 2007
  • Open bids before May 15, 2007.
  • Award construction contracts before June 1, 2007.
  • Start projects before July 1, 2007.

20. Goal: Complete a fixed asset inventory.

Objectives:

  • Collect proposals from at least two vendors before February 1, 2007.
  • Before February 5, 2007, send the proposals to the Borough Attorney for review.
  • Before March 1, 2007, meet with the Department Heads to explain the project and timeline.
  • Initiate the project before March 15, 2007.
  • Complete the project before June1, 2007.

21. Goal: Complete installation of sidewalks on Watchung Avenue from Lafayette Avenue to Washington Avenue.

Objectives:

  • Submit grant application before January 15, 2007.
  • Prepare plan design and specifications before March 1, 2007.
  • Review plan with neighborhood before March 15, 2007.
  • Advertise for bids before April 1, 2007.
  • Award contract before May 1, 2007.
  • Initiate work before June 15, 2007.
  • Complete the project before September 1, 2007.

22. Goal: Complete the Lum Field project.

Objectives:

  • Initiate the construction before February 1, 2007.
  • Install artificial turf before May 1, 2007.
  • Open field for play before May 15, 2007.

23. Goal: Design Phase I Elmwood Avenue Project.

Objectives:

  • Prepare the preliminary draft plan and discuss with the Mayor and Borough Council before April 1, 2007.
  • Before May 1, 2007, meet with the neighborhood to explain the plan.
  • Advertise for bids before June 1, 2007.
  • Initiate the work before July 1, 2007.
  • Complete the project before December 1, 2007.

24. Goal: Install surveillance cameras at the train station.

Objectives:

  • Before February 15, 2007, contact NJ Transit and discuss sharing cost for the installation of the cameras.
  • Develop a timeline for the installation of the cameras by March 1, 2007.
  • Complete the project before June 1, 2007.

25. Goal: Implement Recreation policies, procedures and field master plan.

  • Objectives: Before February 1, 2007, hold a meeting with the Mayors, Recreation Liaisons and Administrators to discuss each town’s vision for the joint recreation program.
  • The Administrators will meet with both Recreation Directors to initiate the development of written policies and procedures by February 15, 2007.
  • The Administrators will prepare financial analysis

26. Goal: Develop plan to resolve the sanitary sewer back-up problem on Roosevelt, Wilson and Hedges.

Objectives:

  • Before March 2007, the DPW will camera the existing lines.
  • Before April, the Borough Engineer will develop an engineering plan and submit the plan to the Mayor and Borough for review.
  • If the plan is approved before May 2007, the Borough Engineer will prepare a timeline and submit the timeline to the Mayor and Borough Council.

27. Goal: Continue to investigate the cost and timeline for the implementation of GIS for the water, sewer and stormwater systems. Objectives:

  • Before May 1, 2007, the Borough Engineer will obtain price quotes for the development and implementation of the GIS system.
  • Before June 2007, the Borough Engineer will submit the price quotes to the Administrator, Mayor and Borough Council for review.
  • The matter will be scheduled for the June Borough Council meeting.
  • If the project is approved, the Borough Engineer will develop an implementation time and submit the timeline before July 1, 2007.
 
  --------------------------------------------------------------------------------------------------